|
|
|
Hey Contractors How To Fill Out Aia Pay Apps Part 1
f we grabbed the first 10 small subcontractors you 1. Your project manager cuts your crossed paths with and request to a value he can tested them on filling out AIA understand. You receive a partial pay applications, 7 or more would payment. probably fail the test. At least, that's about the error rate I've 2. Your project manager informs seen while reviewing pay you that you if you don’t get a applications. corrected application in by the deadline, you will have to wait AIA pay applications are another 30 days for payment. You frustratingly difficult to fill may not receive any payment. out. To fill one out correctly, you must ignore change orders 3. Your project manager makes the that have been approved, but not corrections himself and may hold processed. You must ignore it against you in the future when receivables still outstanding you need a favor or are looking from previous applications. for work. Like the rest of us, project managers like working Basically, you have to divorce with people who don't create yourself from reality. headaches. Pay apps are an important You really have no choice other component of cash management. than learning how to fill out the When you screw up your pay app, AIA form correctly. three things might happen, none of which put you in good standing I am going to show you how to with your general contractor, and fill one out correctly. In Part two of which damage your cash 1, we attack the first page (AIA position: form G702) and in Part 2 we will
work on the second page (AIA form that have been priced and G703). FORMALLY approved by the GC. If the project manager is sitting on Before we get started, grab a your change order paper work, copy of the form. If you don’t call him at least a week before have access to one, drop me an your pay application is due and email and I’ll send you the form. URGE HIM to complete the paper work. Being the squeaky wheel is Line 1, Original Contract Sum. often your only recourse. The price the GC agreed to pay Assume the GC has processed and you for the scope of work you signed $100,000 in change orders. agreed to perform. This includes all accepted alternates. Line 3, Contract Sum to Date Pull out your contract. Look at This should be easy. Add the it. This number should NEVER numbers on lines 1 and 2. This is change from your first pay your OFFICIAL contract sum at the application to your last. date of this pay application. Assume your contract was for Your contract sum to date is $900,000. $1,000,000 ($900,000 plus $100,000) Line 2, Net Change by Change Orders. Line 4, Total Completed and Stored to Date Here it is. The line that creates much frustration. This value comes from the left side of column G on page 2. The Add up all of the change orders box is the fourth from the left,
bottom row. Your contract may allow you to reduce the retention to 5% near For now assume that you have substantial completion. completed $500,000 of work and have stored $50,000 of materials In the blank next to the dollar in approved storage sites. sign, you need to write down the dollar value of retention that Your line 4 total would be applies to your completed work. $550,000. To arrive at that number, turn to page 2 and add together the Line 5, Retainage (three lines). values from the bottoms of columns D and E. Multiple by 0.1 Your contract should set the if the retention is 10% or by terms of retention. If it 0.05 if the retention is 5%. doesn’t, demand that no retention be withheld! If the GC failed to Assuming 10% retention and put retention in your contract, $500,000 of completed work, write do not allow him to use it. down $50,000. On a side note, if you happen to Line 5b, _% of Stored Materials. be providing a performance bond, retention is not justified. The Repeat the process used for Line bond serves the same purpose as 5a except use the value from the the retention. bottom of column F on page 2 . Line 5a, _% of Completed Work. Usually, the retention for completed work and stored In the blank next to the "a.", materials is the same. Write down write down the current retention whichever rate is contracted next percentage. Typically, it is 10%. to the "b.". In the blank next to
the dollar sign, write down the retention for your stored Line 7 Less Previous Certificates materials. for Payment Assuming 10% retention and The pay application has now $50,000 of completed work, write entered the twilight zone. down $5,000. Confusion is caused by generals and owners who take so long to Line 5 Total Retainage. pay that you are submitting your next pay application before the Add together the totals from previous one gets paid. lines 5a and 5b. This value should match your total of column Natural instinct is to write down I on page 2. payments received to date on line 7 and ignore pay requests being For our example, the figure would processed. Don’t do that. Trust be $55,000. the paper trail. This pay application doesn’t care whether Line 6 Total Earned Less you’ve been paid. It only cares Retainage whether you’ve earned additional payment. What you’ve earned, as far as approved change orders are Go back to your immediately concerned, is on line 4. What the preceding pay application and client is allowed to retain is on write down the value from Line 6 line 5. Subtract the Total Total Earned Less Retainage on Retainage ($55,000) from your that application. For the sake of earned revenue ($550,000) and our example, assume you had enter the difference ($495,000) submitted to date on $400,000. on Line 6.
Line 8 Current Payment Due in full. What a dream world the AIA Take your Line 7 value ($400,000) lives in. and subtract it from your line 6 value ($495,000). Write down the Frequently, clients and GCs only difference on Line 8 $95,000). pay part of your application. The AIA form never reflects partial This represents the value you payment of an application. It should be paid for worked earned wasn’t designed to. Keep track of during this pay period AND any what’s been paid vs. what’s been change in retainage during the earned and invoiced (applied pay period. for). Line 9 Balance to Finish The table at the bottom of page Including Retainage one is fairly straight forward. You will need to separate the Take the contract sum to date change orders that add money to from Line 3 ($1,000,000) and your contract from those that subtract the Total Earned Less subtract money from your Retainage from Line 6 ($495,000). contract. The Net Changes by This tells the General Contractor Change Order should be exactly that he is contracted to pay you equal to the value you entered on an additional $505,000 AFTER line 2. paying this application. In summary, following the This is another confusing line instructions and you have a shot because it acts as if all change at getting paid everything you're orders have been formally owed. processed and that all previous pay applications have been paid
About the Author:
Ron Roberts, The Contractor's Business Coach, teaches contractors how to turn their businesses into a profit spewing machines. To receive Ron's FREE Contractor Best Practices Newsletter visit http://www.FilthyRichContractor.com.
Read more articles by: Ron Roberts
Article Source: www.iSnare.com |
|